[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938277":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938277,606,1,"单选题","缺陷责任期自（ ）起计算。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","验收合格之日",false,{"key":16,"text":17,"correct":14},"B","提交竣工验收申请报告",{"key":19,"text":20,"correct":21},"C","实际竣工日期",true,{"key":23,"text":24,"correct":14},"D","使用之日","本题考查的是施工合同履行。缺陷责任期自实际竣工日期起计算。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]