[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938276":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938276,606,1,"单选题","有关工程开工，下列说法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","监理人应在开工日期 14 天前向承包人发出开工通知",false,{"key":16,"text":17,"correct":14},"B","工期自监理人发出的开工通知起计算",{"key":19,"text":20,"correct":21},"C","承包人向监理人提交工程开工报审表，经监理人审批后执行",true,{"key":23,"text":24,"correct":14},"D","开工报审表需说明质量保证措施","本题考查的是施工合同履行。监理人应在开工日期7天前向承包人发出开工通知。工期自监理人发出的开工通知中载明的开工日期起计算。承包人应按合同进度计划，向监理人提交工程开工报审表，经监理人审批后执行。开工报审表应详细说明按合同进度计划正常施工所需的施工道路、临时设施、材料设备、施工人员等施工组织措施的落实情况以及工程的进度安排。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]