[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938274":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938274,606,1,"单选题","下列关于 FIDIC 指定分包商的表述，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","指定分包商不可由工程师选定",false,{"key":16,"text":17,"correct":18},"B","指定分包商不应与业主签订合同",true,{"key":20,"text":21,"correct":14},"C","由指定分包商与承包商不签订合同",{"key":23,"text":24,"correct":14},"D","指定分包商与一般分包商地位不等同","本题考查的是 1999 年版 FIDIC 施工合同条件的主要内容。选项 AC 错误，指定分包商是由业主（或工程师）指定完成某项特定工作内容，并与承包商签订分包合同的特殊分包商；选项 D 错误，指定分包商与一般分包商处于同等地位，工程师对其监督、协调工作应纳人对承包商的管理之中。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]