[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938259":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},938259,606,1,"单选题","根据《标准施工招标文件》(2007 年版)，发生( )违约情况时，承包人可书面通知发包 人解除合同。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发包人未能按合同约定支付预付款或合同价款",false,{"key":16,"text":17,"correct":14},"B","发包人原因造成停工的",{"key":19,"text":20,"correct":14},"C","监理人无正当理由没有在约定期限内发出复工指示，导致承包人无法复工的",{"key":22,"text":23,"correct":24},"D","发包人无法继续履行或明确表示不履行或实质上已停止履行合同的",true,"发包人无法继续履行或明确表示不履行或实质上已停止履行合同的，承包人可书面 通知发包人解除合同。发包人其他违约：承包人书面通知发包人纠正违约行为。发包人收到承包 人通知后的 28 天内仍不履行合同义务，承包人有权暂停施工。承包人暂停施工满 28 天后，发包 人仍不纠正违约行为的，承包人可向发包人发出解除合同通知。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]