[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938257":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938257,606,1,"单选题","承包人应在收到变更指示或变更意向书后的( )天内，向监理人提交变更报价书。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","56",false,{"key":16,"text":17,"correct":14},"B","7",{"key":19,"text":20,"correct":21},"C","14",true,{"key":23,"text":24,"correct":14},"D","28","承包人应在收到变更指示或变更意向书后的 14 天内，向监理人提交变更报价书。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]