[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938256":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938256,606,2,"多选题","关于工程计量的表述，正确的是( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","单价子目结算工程量是计量的工程量",true,{"key":16,"text":17,"correct":14},"B","总价子目的计量和支付应以总价为基础",{"key":19,"text":20,"correct":21},"C","单价子目的计量周期按批准的支付分解报告确定",false,{"key":23,"text":24,"correct":21},"D","总价子目已完成工程量按月计量",{"key":26,"text":27,"correct":14},"E","已标价工程量清单中的单价子目工程量为估算工程量","ABE","对于单价子目和总价子目，合同约定了不同的计量方式： (1)已标价工程量清单中的单价子目工程量为估算工程量。结算工程量是承包人实际完成的， 并按合同约定的计量方法进行计量的工程量。单价子目已完成工程量按月计量。 (2)总价子目的计量和支付应以总价为基础，承包人实际完成的工程量是进行工程目标管理 和控制进度支付的依据。总价子目的计量周期按批准的支付分解报告确定。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]