[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938250":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938250,606,2,"多选题","关于工程项目合同体系的表述，正确的包括( )",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","监理合同是委托合同的一种，监理合同的标的是服务",true,{"key":16,"text":17,"correct":14},"B","监理合同的标的是服务",{"key":19,"text":20,"correct":14},"C","施工合同即工程承包合同，施工合同是双务合同",{"key":22,"text":23,"correct":24},"D","材料采购合同的条款一般涉及材料的生产阶段",false,{"key":26,"text":27,"correct":14},"E","施工合同是工程建设质量控制、进度控制、投资控制的主要依据","ABCE","货物采购包括材料采购和设备采购两部分。材料采购合同的条款一般限于材料交货 阶段，主要涉及交接程序、检验方式和质量要求、合同价款的支付等。大型设备的采购，除了交 货阶段的工作外，往往还需包括设备生产阶段、设备安装调试阶段、设备试运行阶段、设备性能 达标检验和保修等方面的条款约定。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]