[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938248":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938248,606,1,"单选题","对于货物采购合同，如由于买方原因合同设备在三次考核中均未能达到技术性能考核指标，卖方有义务在验收款支付函签署后（ ）应买方要求提供相关技术服务，协助买方采取一切必要措施使合同设备达到技术性能考核指标。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","6 个月内",false,{"key":16,"text":17,"correct":18},"B","12 个月内",true,{"key":20,"text":21,"correct":14},"C","18 个月内",{"key":23,"text":24,"correct":14},"D","24 个月内","本题考查的是设备采购合同的主要内容。卖方有义务在验收款支付函签署后12个月内应买方要求提供相关技术服务，协助买方采取一切必要措施使合同设备达到技术性能考核指标",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]