[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938247":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938247,606,2,"多选题","根据《标准设备采购招标文件》，关于开箱检验的表述正确的包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合同设备交付后应进行开箱检验",true,{"key":16,"text":17,"correct":18},"B","开箱检验不在合同设备交付时进行，买方应在开箱检验 7 日前将开箱检验的时间和地点通 知卖方",false,{"key":20,"text":21,"correct":14},"C","在开箱检验中，买方和卖方应共同签署数量、外观检验报告",{"key":23,"text":24,"correct":14},"D","开箱检验不在合同设备交付时进行，应由买方负责按交货时外包装原样妥善保管",{"key":26,"text":27,"correct":14},"E","开箱检验的检验结果不能免除卖方依照合同约定对买方负有的任何义务或责任","ACDE","开箱检验不在合同设备交付时进行，买方应在开箱检验 3 日前将开箱检验的时间和 地点通知卖方。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]