[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938245":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},938245,606,1,"单选题","根据《标准施工招标文件》(2007 年版)，发包人可向承包人提出费用和(或)工期索赔的 是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","由于承包人原因导致工期延误",false,{"key":16,"text":17,"correct":14},"B","由于承包人的原因导致试运行失败的",{"key":19,"text":20,"correct":14},"C","属承包人原因造成的工程缺陷或损坏",{"key":22,"text":23,"correct":24},"D","承包人违约",true,"A.由于承包人原因导致工期延误——赶工费用+逾期竣工违约金 B.由于承包人的原因导致试运行失败的——费用 C.属承包人原因造成的工程缺陷或损坏——费用",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]