[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938240":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938240,606,1,"单选题","承包人接受了竣工付款证书后，应被认为已无权再提出在合同工程( )所发生的任何索 赔。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","履约证书颁发前",false,{"key":16,"text":17,"correct":14},"B","履约证书颁发后",{"key":19,"text":20,"correct":21},"C","接收证书颁发前",true,{"key":23,"text":24,"correct":14},"D","接收证书颁发后","承包人提出索赔的期限： (1)承包人接受了竣工付款证书后，应被认为已无权再提出在合同工程接收证书颁发前所发 生的任何索赔。 (2)承包人提交的最终结清申请单中，只限于提出工程接收证书颁发后发生的索赔。提出索 赔的期限自接受最终结清证书时终止。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]