[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938235":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938235,606,1,"单选题","根据《标准材料采购招标文件》，除合同另有约定外，供货周期不超过( )个月的签约 合同价为固定价格。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","6",{"key":19,"text":20,"correct":21},"C","12",true,{"key":23,"text":24,"correct":14},"D","24","材料采购合同的合同价格：除合同另有约定外，供货周期不超过 12 个月的签约合 同价为固定价格。供货周期超过 12 个月且合同材料交付时材料价格变化超过合同约定的幅度的， 双方应按照合同条款中约定的调整方法对合同价格进行调整。 设备采购合同的合同价格：除合同另有约定外，签约合同价为固定价格。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]