[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938231":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938231,606,2,"多选题","有关资格审查的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","资格预审是指在招标前对潜在投标人进行的资格审查",false,{"key":16,"text":17,"correct":18},"B","资格后审是指在开标后对投标人进行的资格审查",true,{"key":20,"text":21,"correct":14},"C","进行资格预审的，不再进行资格后审",{"key":23,"text":24,"correct":18},"D","招标人不得以不合理的条件限制、排斥潜在投标人或者投标人",{"key":26,"text":27,"correct":14},"E","招标人可以以没有载明的资格条件对潜在投标人或者投标人进行资格审查","BD","本题考查的是投标申请人资格审查。选项 A 错误，资格预审是指在投标前对潜在投标人进行的资格审查。选项 C 错误，进行资格预审的，一般不再进行资格后审，但招标文件另有规定的除外。采取资格预审的，招标人应当在资格预审文件中载明资格预审的条件、标准和方法；采取资格后审的，招标人应当在招标文件中载明对投标人资格要求的条件、标准和方法。选项 E 错误，招标人不得改变载明的资格条件或者以没有载明的资格条件对潜在投标人或者投标人进行资格审查。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]