[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938204":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938204,606,2,"多选题","有关招标文件编制和发放过程中的时间要求，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","自招标文件出售之日起至停止出售之日止，最短不得少于 5 日",true,{"key":16,"text":17,"correct":18},"B","投标人拒绝延长投标有效期的，其投标保证金将被没收",false,{"key":20,"text":21,"correct":18},"C","招标人应当在投标截止时间至少 20 日前，对已发出的招标文件进行必要的澄清或者修改",{"key":23,"text":24,"correct":18},"D","潜在投标人或者其他利害关系人对招标文件有异议的，应当在投标截止时间 15 日前提出",{"key":26,"text":27,"correct":14},"E","招标人应当自收到异议之日起 3 日内作出答复","AE","本题考查的是招标文件编制与发放。选项 B 错误，投标人拒绝延长投标有效期的的，其投标失效，但投标人有权收回其投标保证金；选项 C 错误，招标人应当在投标截止时间至少 15 日前，对已发出的招标文件进行必要的澄清或者修改；选项 D 错误，潜在投标人或者其他利害关系人对招标文件有异议的，应当在投标截止时间 10 日前提出。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]