[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938202":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938202,606,2,"多选题","采用经评审的最低投标价法，评标委员会应当拟定一份“标价比较表”，连同书面评标报告提交招标人。“标价比较表”的内容有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","投标人的投标报价",true,{"key":16,"text":17,"correct":14},"B","对商务偏差的价格调整和说明",{"key":19,"text":20,"correct":14},"C","经评审的最终投标价",{"key":22,"text":23,"correct":24},"D","对技术偏差的调整",false,{"key":26,"text":27,"correct":24},"E","对各评审因素的评估","ABC","本题考查的是开标、评标与定标。“标价比较表”应当载明投标人的投标报价、对商务偏差的价格调整和说明以及经评审的最终投标价",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]