[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938188":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938188,606,1,"单选题","采用经评审的最低投标价法的，评标委员会应当根据招标文件中规定的评标价格调整方法，对所有投标人的( )作必要的价格调整。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标报价和投标文件的商务部分",true,{"key":16,"text":17,"correct":18},"B","投标文件的技术部分",false,{"key":20,"text":21,"correct":18},"C","投标报价和投标文件的技术部分",{"key":23,"text":24,"correct":18},"D","投标文件的技术部分和商务部分","采用经评审的最低投标价法的，评标委员会应当根据招标文件中规定的评标价格调 整方法，对所有投标人的投标报价以及投标文件的商务部分作必要的价格调整。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]