[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938164":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938164,606,1,"单选题","项目团队发展的基础是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","将团队作为一个完整的整体来开发",false,{"key":16,"text":17,"correct":18},"B","个人能力在管理和技术方面的提高",true,{"key":20,"text":21,"correct":14},"C","提高项目团队的能力",{"key":23,"text":24,"correct":14},"D","使团队保持和发展工作动力","项目团队能力的开发包括两个方面：一是提高项目参与者个人的贡献力；二是提高 项目团队整体能力。个人能力在管理和技术方面的提高是项目团队发展的基础。为了使项目团队 能力满足项目要求，团队作为一个完整的整体来开发是项目团队实现预定目标的关键。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]