[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938135":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938135,606,2,"多选题","关于工程项目目标系统的说法，正确的是（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","是一种层次结构",true,{"key":16,"text":17,"correct":18},"B","至少由两个层次构成",false,{"key":20,"text":21,"correct":18},"C","系统目标是唯一的",{"key":23,"text":24,"correct":14},"D","子目标仅适用于工程项目的某一方面",{"key":26,"text":27,"correct":18},"E","子目标用于确定工程项目的详细构成","AD","本题考查的是工程项目管理的基本原理。工程项目目标系统是一种层次结构，目标系统至少由系统目标、子目标和可执行目标三个层次构成，系统目标通常可以分为工程项目功能目标、技术目标、经济目标、社会目标和生态目标等。子目标由系统目标分解得到，仅适用于工程项目的某一方面，相当于目标系统中的子系统目标。可执行目标应具有可操作性，也称作操作目标，用于确定工程项目的详细构成。更细的目标分解，一般在可行性研究以及技术设计和计划中形成，并得到进一步解释和定量化，逐渐转化为具体的工作任务。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]