[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938131":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938131,606,2,"多选题","工程项目是指为了形成特定的生产能力或使用效能而进行投资和建设，包含（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","建筑工程",true,{"key":16,"text":17,"correct":14},"B","安装工程",{"key":19,"text":20,"correct":21},"C","科研项目",false,{"key":23,"text":24,"correct":21},"D","嫦娥奔月工程",{"key":26,"text":27,"correct":14},"E","设备购置","ABE","本题考查的是工程项目的概念。工程项目，主要是指为了形成特定的生产能力或使用效能而进行投资和建设，并形成固定资产的各类项目，包含建筑安装工程和设备购置",{"id":6,"name":31,"category":13,"favorite":32},"工程项目组织与管理",0]