[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938124":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938124,606,2,"多选题","PRINCE2的管理过程中，贯穿于项目始终，支持其他六个过程的是（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","DP",true,{"key":16,"text":17,"correct":18},"B","CP",false,{"key":20,"text":21,"correct":18},"C","IP",{"key":23,"text":24,"correct":18},"D","MP",{"key":26,"text":27,"correct":14},"E","PL","AE","本题考查的是国际上常用的工程项目管理知识体系。PRINCE2中涉及8类管理要素（component）、8个管理过程（process）以及4种管理技术（technology）。这八个过程是：指导项目（DP）、开始项目（SU）、启动项目（IP）、管理项目阶段边线（SB）、控制一个阶段（CS）,管理产品交付（MP）、结束项目（CP）、计划（PL）。其中，DP和PL过程贯穿于项目始终，支持其他六个过程。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]