[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938122":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938122,606,1,"单选题","项目目标系统的建立方法是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","WBS",true,{"key":16,"text":17,"correct":18},"B","关键路径法",false,{"key":20,"text":21,"correct":18},"C","鱼刺图",{"key":23,"text":24,"correct":18},"D","网络技术","本题考查的是工程项目管理的基本原理。可以采用工作分解结构（WBS）方法建立工程项目目标系统",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]