[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938061":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938061,606,1,"单选题","（2011年真题）工程项目具体质量计划的制订工作不包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定影响工程项目质量的因素",true,{"key":16,"text":17,"correct":18},"B","明确项目团队各层次的质量管理职能",false,{"key":20,"text":21,"correct":18},"C","编制收集记录数据的标准表格",{"key":23,"text":24,"correct":18},"D","明确项目团队各层次间的配合和接口","质量计划的内容包括： 1)明确各层次的质量目标和质量管理职能。 2)明确各层次之间的配合和接口。 3)明确实现质量目标的过程顺序，明确过程中进行质量监测的环节和频率以及标准。 4)确定和提供实现质量目标必需的资源。 5)明确记录和报告数据的标准表格。@##",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]