[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938044":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938044,606,1,"单选题","（2013年真题）工程项目试运行总结报告由（ ）负责编制。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":14},"B","设计单位",{"key":19,"text":20,"correct":21},"C","施工单位",true,{"key":23,"text":24,"correct":14},"D","监理单位","本题考查的是工程项目试运行阶段的质量管理。试运行总结报告由承包方试运行项目经理组织编制。参见教材P363。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]