[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938025":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938025,606,1,"单选题","（2017年真题）某路基填筑工程合同工期 5 个月，综合单价初定为 15 元\u002Fm3，结算价每月按表 1 价格指数进行调整，计划工程量和实际工程量如表 2 所示，计划工作与实际工作一致，4 月末工程的费用偏差是( )万元",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","-96.75",true,{"key":16,"text":17,"correct":18},"B","96.75",false,{"key":20,"text":21,"correct":18},"C","-135",{"key":23,"text":24,"correct":18},"D","135","",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]