[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938023":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},938023,606,1,"单选题","（2017年真题）下列关于挣值法评价指标含义的说法，正确的是( )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","费用偏差为正值，表示项目实际费用高于预算费用",false,{"key":16,"text":17,"correct":14},"B","进度偏差为正值，表示项目实际进度落后于计划进度",{"key":19,"text":20,"correct":14},"C","费用绩效指数小于1，表示项目实际费用低于预算费用",{"key":22,"text":23,"correct":24},"D","进度绩效指数小于1，表示项目实际进度落后于计划进度",true,"",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]