[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938022":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},938022,606,1,"单选题","（2009年真题）某工程施工到 2009 年 3 月 31 日时，得到如下数据：计划工作预算费用为 2 800 万元，已完工作预算费用为 3 400 万元，已完工作实际费用为 3 000 万元。则工程此时的进度偏差为( )万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","-200",false,{"key":16,"text":17,"correct":14},"B","200",{"key":19,"text":20,"correct":14},"C","400",{"key":22,"text":23,"correct":24},"D","600",true,"",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]