[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938021":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938021,606,1,"单选题","（2011年真题）某工程施工到 2011 年 3 月，已完工作预算费用为 6000 万元，计划工作预算费用为 5800万元，已完工作实际费用为 6200 万元，则此时的费用绩效指数为( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.94",false,{"key":16,"text":17,"correct":18},"B","0.97",true,{"key":20,"text":21,"correct":14},"C","1.03",{"key":23,"text":24,"correct":14},"D","1.07","",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]