[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938015":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938015,606,1,"单选题","（2008年真题）某工程施工到 2008 年 4 月，已完工作预算费用为 6000 万元，计划工作预算费用为 5800万元.已完工作实际费用为 6200 万元，则该工程此时的进度绩效指数为( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.94",false,{"key":16,"text":17,"correct":14},"B","0.97",{"key":19,"text":20,"correct":21},"C","1.03",true,{"key":23,"text":24,"correct":14},"D","1.07","",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]