[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938014":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938014,606,1,"单选题","（2008年真题）2008 年 3 月底，某项目计划工作预算费用为 4800 万元，已完工作预算费用为 4200 万元，已完工作实际费用为 5200 万元。据此判断，该项目此时( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度提前，费用超支",false,{"key":16,"text":17,"correct":18},"B","进度拖延，费用超支",true,{"key":20,"text":21,"correct":14},"C","进度提前，费用节约",{"key":23,"text":24,"correct":14},"D","进度拖延，费用节约","",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]