[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938012":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938012,606,1,"单选题","（2012年真题）某工程项目总费用预算为 1000 万元，计划工期为 10 个月，第 8 个月月末已完工作实际费用为 900 万元，若此时预测项目能否按预算完成，还需要( )信息",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计划工作预算费用",false,{"key":16,"text":17,"correct":18},"B","已完工作预算费用",true,{"key":20,"text":21,"correct":14},"C","已使用的准备金",{"key":23,"text":24,"correct":14},"D","已消耗的资源数量","",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]