[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938005":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938005,606,1,"单选题","（2005年真题）如果与费用偏差相联系，工程项目费用控制中的进度偏差是指( )之间的差异。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","已完工程实际费用与拟完工程计划费用",false,{"key":16,"text":17,"correct":18},"B","拟完工程计划费用与已完工程计划费用",true,{"key":20,"text":21,"correct":14},"C","已完工程实际时间与拟完工程计划时间",{"key":23,"text":24,"correct":14},"D","已完工程计划费用与未完工程计划费用","进度偏差=拟完工程计划费用一已完工程计划费用。@##",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]