[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938004":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938004,606,2,"多选题","（2017年真题）如果要减少项目进度计划的计算工期，可以采取的措施有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","增加人员",true,{"key":16,"text":17,"correct":18},"B","消减时差",false,{"key":20,"text":21,"correct":14},"C","赶工",{"key":23,"text":24,"correct":14},"D","增加平行作业",{"key":26,"text":27,"correct":14},"E","取消部分工作","ACDE","本题考查的是项目进度控制方法。进度计划的调整措施包括调整工作的逻辑关系，增、减工作，调整资源的投入、调整工作的持续时间等。 @##",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]