[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938003":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938003,606,2,"多选题","（2016年真题）工作顺序安排的依据包括( )",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作清单",true,{"key":16,"text":17,"correct":18},"B","成果说明文件",false,{"key":20,"text":21,"correct":14},"C","各项工作之间的逻辑关系",{"key":23,"text":24,"correct":14},"D","其他约束与假设",{"key":26,"text":27,"correct":18},"E","成本强度","ACD","工作顺序安排的依据 (1)进度管理计划。(2)工作清单。(3)工作属性。(4)里程碑清单。(5)项目范围说明书。(6)环境因素。(7)组织过程资产。@##",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]