[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938002":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938002,606,2,"多选题","（2018年真题）关于项目进度计划及其优化的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","计划中的关键工作指的是自由时差为零的工作",false,{"key":16,"text":17,"correct":18},"B","计划优化时应考虑有充足备用资源的工作",true,{"key":20,"text":21,"correct":14},"C","工期优化通过压缩持续时间长的工作进行",{"key":23,"text":24,"correct":18},"D","横道图是传统的进度计划表示方法",{"key":26,"text":27,"correct":14},"E","工作间逻辑关系不能确定时，应采用计划评审技术编制计划","BD","本题考查的是进度计划优化。选项A，网络计划中总时差最小的工作是关键工作；选项C，工期优化一般通过压缩关键工作的持续时间来进行；选项E，计划评审技术是计划中工作与工作之间的逻辑关系肯定，但每项工作的持续时间不肯定。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]