[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938000":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938000,606,2,"多选题","（2016年真题）工作时间估算的方法有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","类比估算",true,{"key":16,"text":17,"correct":14},"B","利用历史数据估算",{"key":19,"text":20,"correct":21},"C","头脑风暴法",false,{"key":23,"text":24,"correct":14},"D","专家判断估算",{"key":26,"text":27,"correct":14},"E","模拟法","ABDE","本题考查的是工作时间估算。工作时间估算的方法有类比估算、利用历史数据、专家判断估算、模拟法、群体决策技术以及储备分析。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]