[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937999":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937999,606,2,"多选题","（2012年真题）将工程项目实际进度与计划进度进行比较的方法主要有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","关键线路比较法",false,{"key":16,"text":17,"correct":18},"B","横道图比较法",true,{"key":20,"text":21,"correct":14},"C","控制图比较法",{"key":23,"text":24,"correct":18},"D","前锋线比较法",{"key":26,"text":27,"correct":18},"E","列表比较法","BDE","本题考查的是项目进度控制方法。实际进度与计划进度比较常用的方法有：趋势分析（横道图比较法、前锋线比较法、S 型曲线比较法、香蕉曲线比较法、列表比较法）、关键路径、挣值管理。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]