[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937998":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937998,606,2,"多选题","（2013年真题）工程项目进度管理的工作内容主要有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","资源需求分析",false,{"key":16,"text":17,"correct":18},"B","工作时间估算",true,{"key":20,"text":21,"correct":14},"C","工作成本测算",{"key":23,"text":24,"correct":18},"D","工作顺序安排",{"key":26,"text":27,"correct":18},"E","进度计划编制","BDE","本题考查的是进度管理过程。进度管理包括为确保项目按期完成所必须的所有过程，包括规划进度管理、工作定义、工作顺序安排、工作资源估算、工作时间估算、进度计划制定和进度控制等。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]