[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937997":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937997,606,2,"多选题","（2016年真题）定义优先级的标准一般有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","资源的数量和价值量",true,{"key":16,"text":17,"correct":14},"B","资源增减的可能性",{"key":19,"text":20,"correct":14},"C","获得程度",{"key":22,"text":23,"correct":14},"D","可替代性",{"key":25,"text":26,"correct":27},"E","价格问题对项目的影响",false,"ABCD","本题考查的是工作资源估算。优先级的定义可以随着项目的不同而不同，一般有以下几个标准：①资源的数量和价值量；②资源增减的可能性；③获得程度；④可替代性；⑤供应问题对项目的影响。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]