[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937994":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937994,606,2,"多选题","（2005年真题）工程项目进度计划优化中的费用优化是为了寻求( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","资源有限条件下的最短工期安排",false,{"key":16,"text":17,"correct":18},"B","最低成本时的最短工期安排",true,{"key":20,"text":21,"correct":14},"C","资源均衡使用时的最短工期安排",{"key":23,"text":24,"correct":18},"D","满足要求工期时的最低成本安排",{"key":26,"text":27,"correct":14},"E","最低成本条件下资源均衡安排","BD","费用优化又叫工期成本优化，是寻求最低成本的最短工期安排，或按要求工期寻求最低成本的计划安排过程。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]