[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937993":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937993,606,2,"多选题","（2011年真题）某工作的实际进度发生偏差，判断其对后续工作和总工期是否产生影响的依据有( )",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程资源的分布是否均衡",false,{"key":16,"text":17,"correct":14},"B","该工程的实际投资是否到位",{"key":19,"text":20,"correct":21},"C","该工作是否处于关键线路",true,{"key":23,"text":24,"correct":21},"D","进度偏差是否超过该工作的总时差",{"key":26,"text":27,"correct":21},"E","进度偏差是否超过该工作的自由时差","CDE","",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]