[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937992":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937992,606,2,"多选题","（2017年真题）下列进度控制过程的内容中，最先和最后进行的内容为( )",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","出现进度偏差",true,{"key":16,"text":17,"correct":18},"B","分析偏差对其后续工作和总工期的影响",false,{"key":20,"text":21,"correct":18},"C","采取进度调整措施",{"key":23,"text":24,"correct":18},"D","采取相应的经济、组织、合同措施",{"key":26,"text":27,"correct":14},"E","进度监测系统","AE","",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]