[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937991":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937991,606,2,"多选题","（2010年真题）工程项目实际进度与计划进度的比较方法主要有( )",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","关键线路比较法",false,{"key":16,"text":17,"correct":18},"B","横道图比较法",true,{"key":20,"text":21,"correct":18},"C","S曲线比较法",{"key":23,"text":24,"correct":18},"D","前锋线比较法",{"key":26,"text":27,"correct":18},"E","列表比较法","BCDE","",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]