[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937989":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937989,606,2,"多选题","（2006年真题）工程项目进度计划的资源优化是在现有资源条件下寻求( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","最优工期条件下的资源均衡",false,{"key":16,"text":17,"correct":18},"B","工期固定条件下的资源均衡",true,{"key":20,"text":21,"correct":18},"C","资源有限条件下的最短工期",{"key":23,"text":24,"correct":14},"D","资源均衡使用时的最短工期",{"key":26,"text":27,"correct":14},"E","最低成本条件下的最短工期","BC","",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]