[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937988":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937988,606,2,"多选题","（2014年真题）选择缩短持续时间的关键工作进行工程项目工期优化时，应优先选择( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","对质量影响不大的工作",true,{"key":16,"text":17,"correct":14},"B","增加费用最少的工作",{"key":19,"text":20,"correct":21},"C","持续时间最长的工作",false,{"key":23,"text":24,"correct":21},"D","可以最后进行的工作",{"key":26,"text":27,"correct":14},"E","有充足备用资源的工作","ABE","选择应缩短持续时间的关键工作，将其持续时间压至最短，并重新计算网络计划的计算工期和关键线路。若被压缩的工作变成非关键工作，则应延长其持续时间，使之仍为关键工作。 选择应缩短持续时间的关键工作应考虑下列因素： 1)缩短持续时间对质量和安全影响不大的工作； 2)有充足备用资源的工作； 3)缩短持续时间增加费用最少的工作",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]