[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937987":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937987,606,2,"多选题","（2016年真题）进度计划的优化方法包括( )",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工期优化",true,{"key":16,"text":17,"correct":14},"B","费用优化",{"key":19,"text":20,"correct":21},"C","工艺优化",false,{"key":23,"text":24,"correct":21},"D","质量优化",{"key":26,"text":27,"correct":14},"E","资源优化","ABE","进度计划的优化方法有： 工期优化、费用优化、资源优化三种。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]