[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937986":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},937986,606,2,"多选题","（2012年真题）编制工程项目进度计划的方法主要有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","关键线路法",true,{"key":16,"text":17,"correct":14},"B","计划评审技术",{"key":19,"text":20,"correct":21},"C","头脑风暴法",false,{"key":23,"text":24,"correct":14},"D","图示评审技术",{"key":26,"text":27,"correct":21},"E","定额计算法","ABD","编制进度计划的方法：关键线路法(CPM)，计划评审技术(PERT)，图示评审技术(GERT)等。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]