[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937983":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},937983,606,1,"单选题","（2017年真题）某工程双代号时标网络计划如图所示，其中工作E的总时差和自由时差（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1周，1周",false,{"key":16,"text":17,"correct":14},"B","2周，0周",{"key":19,"text":20,"correct":21},"C","2周，1周",true,{"key":23,"text":24,"correct":14},"D","3周，2周","本题考查的是工作顺序安排。E 工作的总时差为2 周，自由时差为1 周。@##",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]