[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937982":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},937982,606,1,"单选题","（2011年真题）下列工程进度计划表示方法中，不能直接在图上显示各项工作的开始和完成时间的方法是( )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","横道图法",false,{"key":16,"text":17,"correct":14},"B","时标网络图法",{"key":19,"text":20,"correct":14},"C","单代号网络图法",{"key":22,"text":23,"correct":24},"D","进度曲线法",true,"",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]