[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937980":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},937980,606,1,"单选题","（2016年真题）下列关于虚箭线的说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","不消耗时间",false,{"key":16,"text":17,"correct":14},"B","不消耗资源",{"key":19,"text":20,"correct":14},"C","表达逻辑关系",{"key":22,"text":23,"correct":24},"D","表达组织关系",true,"本题考查的是工作顺序安排。虚工作用虚箭线表示，它既不消耗时间，也不消耗资源。虚工作是人为的虚设工作，只表示相邻前后工作间的逻辑关系。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]