[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-937978":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},937978,606,1,"单选题","（2014年真题）工程项目双代号网络计划如图所示，工作F 的最迟开始时间是（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4",true,{"key":16,"text":17,"correct":18},"B","6",false,{"key":20,"text":21,"correct":18},"C","8",{"key":23,"text":24,"correct":18},"D","10","本题考查的是制定进度计划的方法。由图可知关键线路为C→F→G，总工期为15 天，F 是关键工作，所以F 工作的最迟开始时间等于最早开始时间，F 工作的最早开始时间为4，所以F 工作的最迟开始时间也是第4 天。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]